搜索关注在线英语听力室公众号:tingroom,领取免费英语资料大礼包。
(单词翻译)
The U.S. Special Inspector1 General for Iraq Reconstruction2 has criticized the State Department for its management of nearly $3 billion in contracts and grants in Iraq.
In two reports, auditors4 cited weak and ineffective State Department oversight5 of a $2.5 billion contract for police training and a grant of $250 million for programs to build democratic institutions.
The first report found that lax oversight of the police training contract with DynCorp International has left the contract's funds vulnerable to fraud and abuse.
Special Inspector General for Iraq Reconstruction Stuart Bowen says the issue of oversight has long plagued the DynCorp contract.
"This is not a new issue. It's one we pointed6 out previously7 in reviews of the police training oversight there. But it's a troubling issue because not enough progress has been made in addressing the problems we have uncovered in our prior reports," he said.
Bowen points to questionable8 invoices9 from DynCorp, such as an order for electric power generators10 it already had and payments for real estate that far exceeded local market value.
Bowen say the State Department does not have enough personnel to monitor the costs associated with the police training contract.
"What this audit3 is really about, though, is weaknesses in controls over the review of DynCorp's invoices. These are enormous invoices with thousands of line items charging millions of dollars, and you have one person essentially11 actively12 reviewing them. And that's insufficient," he said.
State Department spokesman P.J. Crowley said Monday that the department acknowledges the need for more auditors in Iraq. But he took issue with the report's assertions regarding vulnerability to fraud and waste.
"I don't think that we agree with the characterization in that report. But we will continue to work with the I.G. [i.e., Inspector General] on it," he said.
In a written statement, DynCorp says its performance of the contract has been "exemplary" and that the firm welcomes thorough scrutiny13 of its billing and invoices.
In the second report, auditors questioned the effectiveness of grants totaling some $248 million to the National Democratic Institute and the International Republican Institute for democracy promotion14.
Bowen says both groups engage in a variety of programs to help build civil institutions in post-Saddam Iraq.
"It's called 'democracy-building' - specifically, training for elections, training for political parties, training for all aspects of the electoral process. Iraq is a fledgling democracy. It has no foundation from which to work in this regard. And there have been five elections in the past six years in Iraq, and that has required essentially a system to be built from scratch coming out of the tyranny that preceded it," he said.
Although these grants are small compared to the police training contract, Bowen says the problems are the same.
"[They are] a much smaller effort, but similar nevertheless in that there is not sufficient oversight being carried out in-country - both in review of expenditures15 and in provision of outcomes. The grants themselves require pretty detailed16 reporting on achievements. And we found that that is just not being done. Very cursory17 reporting is being provided regarding these grants," he said.
Without detailed reporting, Bowen says, the effectiveness of the two programs cannot be accurately18 gauged19. A National Democratic Institute official, who asked not to be named, says his organization's reporting on its activities has been detailed and far in excess of State Department requirements.
Auditors also noted20 that the National Democratic Institute, or NDI, spent almost one-third of grant funds for security, and that the International Republican Institute used more than half of its funds for the same purpose. The NDI official said the organization's security costs were moderate and reasonable in light of the situation in Iraq. In a written statement, the International Republican Institute denies that its security costs were excessive. A previous Inspector General report found that security costs for contractors21 and grantees in Iraq ranged between 24 and 53 percent of the contract or grant.
1 inspector | |
n.检查员,监察员,视察员 | |
参考例句: |
|
|
2 reconstruction | |
n.重建,再现,复原 | |
参考例句: |
|
|
3 audit | |
v.审计;查帐;核对;旁听 | |
参考例句: |
|
|
4 auditors | |
n.审计员,稽核员( auditor的名词复数 );(大学课程的)旁听生 | |
参考例句: |
|
|
5 oversight | |
n.勘漏,失察,疏忽 | |
参考例句: |
|
|
6 pointed | |
adj.尖的,直截了当的 | |
参考例句: |
|
|
7 previously | |
adv.以前,先前(地) | |
参考例句: |
|
|
8 questionable | |
adj.可疑的,有问题的 | |
参考例句: |
|
|
9 invoices | |
发票( invoice的名词复数 ); (发货或服务)费用清单; 清单上货物的装运; 货物的托运 | |
参考例句: |
|
|
10 generators | |
n.发电机,发生器( generator的名词复数 );电力公司 | |
参考例句: |
|
|
11 essentially | |
adv.本质上,实质上,基本上 | |
参考例句: |
|
|
12 actively | |
adv.积极地,勤奋地 | |
参考例句: |
|
|
13 scrutiny | |
n.详细检查,仔细观察 | |
参考例句: |
|
|
14 promotion | |
n.提升,晋级;促销,宣传 | |
参考例句: |
|
|
15 expenditures | |
n.花费( expenditure的名词复数 );使用;(尤指金钱的)支出额;(精力、时间、材料等的)耗费 | |
参考例句: |
|
|
16 detailed | |
adj.详细的,详尽的,极注意细节的,完全的 | |
参考例句: |
|
|
17 cursory | |
adj.粗略的;草率的;匆促的 | |
参考例句: |
|
|
18 accurately | |
adv.准确地,精确地 | |
参考例句: |
|
|
19 gauged | |
adj.校准的;标准的;量规的;量计的v.(用仪器)测量( gauge的过去式和过去分词 );估计;计量;划分 | |
参考例句: |
|
|
20 noted | |
adj.著名的,知名的 | |
参考例句: |
|
|
21 contractors | |
n.(建筑、监造中的)承包人( contractor的名词复数 ) | |
参考例句: |
|
|
本文本内容来源于互联网抓取和网友提交,仅供参考,部分栏目没有内容,如果您有更合适的内容,欢迎 点击提交 分享给大家。